Spotatrain
HS2

Mega Project

Under Construction

HS2

Britain's most ambitious post-war railway, halved in scope and being rebuilt under a 2026 programme reset.

London → Birmingham

Length

225 km

Max speed

360 km/h

Stations

4

Tunnels

10

Bridges

169

Budget

GBP 91,700

Britain's controversial high-speed line from London to Birmingham — halved in scope after Phase 2 was cancelled in 2023 and now midway through a 2026 programme reset.

About This Project

HS2 is the most consequential addition to Britain's mainline railway network in more than a century, and arguably its most divisive. The 225 km Phase 1 line will connect London Euston to Birmingham Curzon Street via two intermediate stations — Old Oak Common in west London and Birmingham Interchange near the NEC in Solihull — with a junction at Handsacre in Staffordshire feeding HS2 trains onto the existing West Coast Main Line for services to Liverpool, Manchester, Preston, and Glasgow.

What is being built today is a much smaller project than what was once promised. The original plan, approved by Parliament in 2017, envisioned a Y-shaped network running from London to Manchester and Leeds, with branches connecting to Heathrow and Scotland. In October 2023, Prime Minister Rishi Sunak announced at the Conservative Party Conference — held in Manchester, no less — that the Phase 2 northern legs would be cancelled, with the savings redirected to a vaguely defined 'Network North' transport programme. The succeeding Labour government confirmed in October 2024 that the cancellation would stand.

Phase 1 is an extraordinary engineering undertaking. Roughly 90 percent of the route runs in tunnel, cutting, or on viaducts and bridges to limit surface impact on one of Europe's most densely populated corridors. The 16.04 km Chiltern Tunnel under the Chiltern Hills AONB became the UK's longest railway tunnel when its twin bores, driven by Herrenknecht TBMs Florence and Cecilia, broke through in February and March 2024. The 3.4 km Colne Valley Viaduct, completed in September 2025, supplanted the 1887 Tay Bridge as Britain's longest railway bridge.

Construction stretches across 350 sites between London and Birmingham. About 30,000 workers and 3,500 UK businesses are on the programme. By the end of February 2026, £43.6 billion (nominal) had been spent, and the government had committed an additional £25.3 billion for the following four fiscal years. The full revised cost and opening date — neither will fall within the original 2026 or 2029-2033 windows — are scheduled for publication at the end of 2026 once Mark Wild's reset is complete.

When the line eventually opens, fifty-four 200 m-long Hitachi-Alstom 'Zefiro V300' derivative trains, built in the UK and capable of 360 km/h, will run up to eighteen times per hour into London. Old Oak Common will serve as the London terminus for several years while the Euston station rebuild — paused pending private finance — catches up. The headline London-to-Birmingham journey will fall from 1 h 21 min to roughly 45 minutes.

Video

Why This Project Matters

HS2's central case has always rested on capacity rather than speed. The West Coast Main Line (WCML) — the existing rail spine running from London to Glasgow via Birmingham, Manchester and Preston — is one of Europe's most heavily-mixed-traffic railways, sharing tracks among inter-city expresses, regional trains, suburban commuters and freight. By the late 2000s, planners argued that incremental upgrades had been exhausted and that a dedicated high-speed line for inter-city traffic was the only way to unlock significant new capacity for freight and regional services on the existing WCML.

Closing the productivity gap between London and the Midlands and the North was the project's second pillar. Successive governments have argued that a 45-minute London-Birmingham journey, combined with better onward connections, would broaden labour markets, lift business investment in cities outside the capital, and offer a partial answer to Britain's stark north-south economic divide. The West Midlands Combined Authority projected a £10 billion regional economic uplift over a decade tied to HS2-driven regeneration around Curzon Street, Birmingham Interchange and the Washwood Heath depot. Critics counter that the Phase 2 cancellation has gutted that rebalancing rationale, leaving Phase 1 functioning mainly as a faster commute for the South East.

Technical Details

HS2 is being built to international high-speed standards: standard 1435 mm gauge, dedicated double-track, no level crossings, electrified at 25 kV / 50 Hz AC overhead, and signalled with ETCS Level 2 (the European Train Control System). The design speed is 360 km/h (225 mph), which would make HS2 trains the fastest in regular European operation, though the 2026 reset is examining whether reducing the design speed to 300 km/h could cut cost and bring services in sooner. Geometry on Phase 1 is unusually demanding: about 90 percent of the alignment runs in tunnel, cutting, or on bridges and viaducts, with maximum gradients around 2.5 percent.

Phase 1's headline structures are the 16.04 km twin-bore Chiltern Tunnel and the 3.4 km Colne Valley Viaduct, alongside four more twin-bore tunnels (Euston, Northolt, Long Itchington Wood, Bromford) and five 'green' tunnels designed to keep the line below the surface through environmentally sensitive landscapes (Copthall, Wendover, Greatworth, Chipping Warden, Burton Green). The route also carries 52 viaducts and 169 bridges, including the Delta Junction viaduct complex outside Birmingham and Curzon 2, the tallest bridge on the network (completed May 2026).

Rolling stock will come from the Hitachi-Alstom High Speed JV: 54 fully-electric 200 m-long electric multiple units derived from Alstom's Zefiro V300 platform, coupleable to form 400 m trainsets. Vehicle bodies are built at Hitachi Newton Aycliffe, bogies at Alstom Crewe Works, and final assembly takes place at Alstom Derby Litchurch Lane. The fleet is designed to be among the most energy-efficient operational high-speed trains in the world thanks to aerodynamic refinement, regenerative braking, and a low train mass per passenger.

Economic Impact

Economic-impact analyses commissioned by HS2 Ltd and the West Midlands Combined Authority forecast a £10 billion regional economic uplift over the decade after opening, anchored on the three HS2 hubs at Curzon Street (Birmingham), Birmingham Interchange (Solihull) and Washwood Heath depot. The Curzon Street redevelopment alone is projected to generate 14,000 jobs and £1.3 billion of local economic activity, and Birmingham was chosen as the location for HS2's construction headquarters, adding another 1,500 jobs. Across the three hubs, planners forecast 30,835 new jobs, 41,000 new homes and 704,000 square metres of commercial floorspace within a 1.5 mile radius.

During construction, the programme has been an unusually large training and apprenticeship pipeline: roughly 30,000 workers and 3,500 UK businesses are currently engaged, 2,032 apprentices have started on the project (against an original target of 2,000), and 5,645 previously unemployed people have secured work on HS2. Critics argue that the cancellation of Phase 2 removed most of the original 'levelling-up' economic case — the larger jobs and connectivity benefits were always concentrated north of Birmingham — and that the project's surviving benefit-cost ratio of around 0.8 means the surviving line will not, on the government's own terms, repay its investment in conventional economic terms.

Environmental Impact

HS2 has framed Phase 1 as 'the world's most sustainable high-speed railway', promising zero-carbon operation from the day services begin and net biodiversity gain along the corridor — including a commitment to plant approximately 7 million trees and shrubs, of which roughly 700,000 had been planted by 2022. The project also commissioned a 900 m-long bat protection structure at Sheephouse Wood in Buckinghamshire to shield the rare Bechstein's bat from passing trains, and is constructing five 'green tunnels' (Copthall, Wendover, Greatworth, Chipping Warden, Burton Green) so that the line passes below the surface through environmentally sensitive landscapes.

The trade-offs have been heavily contested. About 24 hectares of ancient woodland across 25 sites on Phase 1 are being directly impacted, an irreversible loss that HS2 says will be offset by planting and long-term habitat maintenance but which campaign groups including The Wildlife Trusts and Stop HS2 have argued is incommensurable. The Sheephouse Wood structure itself drew a Tree Protection Order from Buckinghamshire Council in 2023 after HS2 felled adjacent trees during enabling works, before being overturned on appeal. Operationally, HS2 still expects to deliver significant modal-shift carbon savings by displacing internal UK flights and inter-city car journeys, though independent analysts have noted that the embedded carbon of construction will take a decade or more of operation to pay back.

Challenges & Controversies

Few infrastructure projects in modern British history have been as politically contested as HS2. Compulsory purchase costs for Phase 1 properties reached roughly £3.9 billion, more than three times the original estimate, and thousands of residents and businesses were displaced from a corridor that cuts through some of the most expensive land in England. Environmental opposition has been equally fierce: about 24 hectares of ancient woodland across 25 sites are being directly impacted by Phase 1 alone, and the bespoke 900 m-long bat protection structure at Sheephouse Wood in Buckinghamshire — designed to shield rare Bechstein's bats from passing trains — drew a Tree Protection Order from Buckinghamshire Council after HS2 felled adjacent trees.

Cost overruns and timeline slippage have repeatedly fed scepticism. The 2012 budget of £32.7 billion has been progressively revised upward — through £42.6 billion in 2013, £55.7 billion in 2015 (the figure on which Parliament voted in 2017), into the £88 billion-plus range by 2019, and beyond £100 billion in the 2020 Oakervee Review. The National Audit Office criticised the original business case as overstated; the latest published benefit-cost ratio for the surviving Phase 1 is around 0.8, well below the 'medium value-for-money' threshold of 1.5. HS2 Ltd has responded that the early figures used 2011 rates and made simple assumptions that did not account for the project's full complexity, that the company is delivering more rigorous environmental mitigation than international peers, and that all six headline 2025 construction milestones were met on time. The reset under Mark Wild is intended to give the government — and the public — a verifiable final cost and opening date for the first time since 2017.

Project Timeline

January 14, 2009announcement

HS2 Ltd established to study a new high-speed line

The outgoing Labour government's Department for Transport set up High Speed Two Limited to develop the case for a new north-south high-speed railway and report back the following year.

Source
January 10, 2012approval

Coalition government formally approves HS2

Transport Secretary Justine Greening confirmed government backing for a Y-shaped HS2 network: London to Birmingham as Phase 1, then branches to Manchester and Leeds as Phase 2. Initial budget set at £32.7 billion.

Source
November 25, 2013approval

Hybrid Bill introduced to Parliament

The High Speed Rail (London-West Midlands) Hybrid Bill was deposited in the House of Commons, beginning a three-year parliamentary process during which select committees heard hundreds of petitions from affected residents, councils and businesses.

Source
February 23, 2017approval

Royal Assent — High Speed Rail (London-West Midlands) Act 2017

The Phase 1 Hybrid Bill received Royal Assent, granting HS2 Ltd compulsory purchase and construction powers between London Euston and Handsacre Junction in Staffordshire. The Bill had passed its Commons Third Reading 399-42 and the Lords by 386-26.

Source
April 15, 2020groundbreaking

Final Notice to Proceed signed; full construction begins

Prime Minister Boris Johnson signed the Final Notice to Proceed following the Oakervee Review, formally clearing the project for full Phase 1 construction. Estimated cost at the time: £88-98 billion.

Source
December 9, 2021construction

Hitachi-Alstom JV awarded rolling stock contract

A 50/50 joint venture between Hitachi Rail and Alstom was awarded a £1.97 billion contract to design, build and maintain 54 high-speed trains for HS2 Phase 1. The trains, based on Alstom's Zefiro V300 platform, will be 200 m long, all-electric, and rated for 360 km/h.

Source
October 4, 2023cancellation

Prime Minister Sunak cancels Phase 2

Speaking at the Conservative Party Conference in Manchester, Prime Minister Rishi Sunak announced that HS2 Phase 2 — the legs to Manchester, Leeds and beyond — would be cancelled, citing cost overruns. Around £36 billion was to be redirected to a 'Network North' transport programme.

Source
March 22, 2024construction

Chiltern Tunnel boring complete (TBM Cecilia breakthrough)

TBM Cecilia broke through the Chiltern Tunnel's north portal, completing the second of two 16.04 km bores. With its sister TBM Florence (which broke through in February), the Herrenknecht machines had spent nearly three years tunnelling under the Chiltern Hills AONB at up to 90 m depth.

Source
October 30, 2024setback

Labour government confirms Phase 2 cancellation; Mark Wild appointed CEO

The incoming Labour government, in office since July 2024, confirmed in its first Budget and subsequent statements that the cancelled Phase 2 would not be resurrected. Mark Wild — who had led the Crossrail recovery — was confirmed as the new CEO of HS2 Ltd, charged with delivering a comprehensive programme reset.

Source
September 10, 2025construction

Colne Valley Viaduct completed — UK's longest rail bridge

The Align JV installed the final precast deck segment of the 3.4 km Colne Valley Viaduct, replacing the 1887 Tay Bridge as Britain's longest railway bridge. The viaduct sits about 10 m above the lakes, the River Colne and the Grand Union Canal.

Source
March 25, 2026funding

DfT 6-monthly Parliamentary report — £43.6 billion spent

The Department for Transport's March 2026 report to Parliament confirmed £43.6 billion (nominal) had been spent on HS2 to the end of February 2026, with an additional £25.3 billion allocated for FY 2026/27 to 2029/30 under the 2026 Spending Review. The fully-reset cost-and-schedule baseline was deferred to end-2026.

Source

Videos

Photos

Photos

Birmingham Proof House junction and Curzon Street station with HS2 approach viaducts

Photo: kitmasterbloke

HS2 approach into the city at Duddeston

Photo: kitmasterbloke

Looking towards HS2 - geograph.org.uk - 6955573

Photo: Christine Matthews

Frequently Asked Questions

When will HS2 open?
Not yet officially known. The original target of 2026 slipped to 2029-2033, and that window was ruled out by HS2 Ltd in 2025. A revised opening date is expected by the end of 2026 once the programme reset led by CEO Mark Wild is complete. Old Oak Common in west London is expected to serve as the initial terminus while the Euston station rebuild catches up.
Will HS2 still go to Manchester or Leeds?
No. Prime Minister Rishi Sunak cancelled Phase 2 — the legs to Manchester and Leeds — in October 2023, and the Labour government confirmed in October 2024 that those northern phases will not be resurrected. HS2 trains will continue beyond Birmingham onto the existing West Coast Main Line via Handsacre Junction, but at conventional rather than high speeds.
How much will HS2 cost in total?
The original 2012 budget was £32.7 billion. By the end of February 2026, £43.6 billion (nominal) had been spent on Phase 1 alone, and the government had allocated a further £25.3 billion for FY 2026/27 to 2029/30. A fully revised total cost is being worked up by HS2 Ltd and is expected by the end of 2026. The current published Phase 1 estimate of £49-£56.6 billion (in 2019 prices) dates from January 2024 and is being reset.
Why has HS2 been so over budget?
Multiple factors. The 2012 budget was based on 2011 prices and simplified assumptions that did not capture the project's full complexity, particularly in ground conditions and environmental mitigation. Inflation, redesigns (notably Euston), and the protracted parliamentary and planning process added cost. The National Audit Office has been critical of HS2's original business case as overstated, and successive governments have argued that the programme was poorly sequenced — a problem the 2025-2026 reset aims to fix.
How fast will HS2 trains go?
The line is designed for 360 km/h (225 mph), which would make HS2 the fastest operational railway in Europe. As part of the 2026 reset, Transport Secretary Heidi Alexander has asked HS2 Ltd to examine whether reducing the design speed to 300 km/h (186 mph) could cut cost and bring services in sooner. London-to-Birmingham journey times are projected at roughly 45 minutes versus 1 h 21 min on the current West Coast Main Line.
Will HS2 trains run all the way into London Euston?
Eventually yes, but not at opening. HS2 Ltd has paused the main Euston station rebuild pending the appointment of a Private Finance Partner via the new Euston Delivery Company. The 6-platform redesigned terminus and surrounding urban regeneration will be procured separately. Until Euston is ready, Old Oak Common in west London — already a 14-platform interchange linked to the Elizabeth line — will be HS2's de facto London terminus.
What is the longest tunnel on the route?
The 16.04 km (9.97 mi) Chiltern Tunnel under the Chiltern Hills AONB, completed in March 2024. It is the longest railway tunnel in the United Kingdom. Two Herrenknecht TBMs — Florence and Cecilia, named for Florence Nightingale and the astronomer Cecilia Payne-Gaposchkin — bored the twin bores at an average rate of 15 metres per day, up to 90 metres below the surface.