Updated
Length
350.8 km
Max speed
320 km/h
Stations
4
Budget
USD 21.1B
A planned 218-mile (351 km) all-electric rail line from Las Vegas to Rancho Cucamonga, designed for up to 200 mph (320 km/h) service. The company states a 2029 target; work at the Las Vegas station site has stopped, per the Review-Journal, while financing is finalised.
About This Project
Scope and route. Brightline West is a planned 218-mile (351 km) all-electric passenger line between a flagship station in Las Vegas and a station next to the Metrolink station in Rancho Cucamonga, California. The Las Vegas station is on a 110-acre site that the company places north of Blue Diamond Road, near the I-15/I-215 interchange at the south end of the Strip. Brightline West divides the civil works into four segments: Nevada (34 miles / 55 km, from the Las Vegas station to the state line), California North (about 110 miles / 177 km, state line to Barstow), California Middle (39 miles / 63 km, Barstow to Hesperia) and California South (34 miles / 55 km, Hesperia to Rancho Cucamonga). Four stations are planned: Las Vegas, Victor Valley (Apple Valley), Hesperia and Rancho Cucamonga, plus a vehicle maintenance facility in Sloan, Nevada. The company puts the trip from Rancho Cucamonga to Las Vegas at about two hours and, with a Metrolink connection, downtown Los Angeles to Las Vegas at about three hours; NDOT gives 2 hours 10 minutes. No official georeferenced route line has been published; the route drawn on the map is an estimate based on OpenStreetMap contributors' data and follows I-15.
Status as of 4 November 2026. Brightline West broke ground in Las Vegas on 22 April 2024 and carried out field investigations along I-15, and in 2025 started site work at the future Las Vegas station (parking garage, box culvert and sewer relocation). NDOT's project page says that once major construction begins it is expected to take about four years. On 26 October 2026 the Las Vegas Review-Journal reported that momentum on the project had all but halted: the garage was unfinished and crews had not been seen on the site in months. The company told the newspaper that it has secured environmental approvals and right-of-way, completed significant design work and finalised agreements with all major construction contractors, and that finalising financing will let it move into full-scale construction; it says it has brought the project to 'the starting line'. KSNV reported on 27 October that the developer is waiting on financing before resuming construction. No suspension has been announced by the company or by any authority; Spotatrain lists the project as on hold because of the reports above, and will review that status by 12 January 2027 or when the Build America Bureau invites a full loan application. The company's target remains 2029, and it has also said delivery would take about four years once financing is in place. The cost was $12 billion at groundbreaking per the company and was listed at $21.05 billion on a US Department of Transportation list reported on 2 October 2025, a figure a company spokesperson confirmed to the Review-Journal.
Video
Why This Project Matters
A corridor between two large markets. At the April 2024 groundbreaking Brightline West cited more than 50 million annual trips between Las Vegas and Southern California, about 17 million Southern California residents living within 25 miles (40 km) of its station sites, and roughly 6 million people attending events at the Las Vegas Convention Center the previous year. The company says its trains would cover the corridor in about two hours; NDOT describes that as twice as fast as the average drive. Las Vegas Convention and Visitors Authority chief Steve Hill told the Review-Journal in October 2026 that the project is important for tourism and could take traffic off I-15.
Federal policy. The $3 billion award came from the Bipartisan Infrastructure Law and was announced by President Biden in December 2023 as part of more than $6 billion for high-speed rail. At the 2024 groundbreaking Transportation Secretary Pete Buttigieg said the project was a new chapter for US transportation, and Brightline founder Wes Edens said the model could be repeated in other city pairs. Brightline also runs a service in Florida between Miami and Orlando.
Technical Details
Rolling stock. Siemens Mobility has been selected to supply ten seven-car American Pioneer 220 (AP 220) electric trainsets, described by Siemens as an evolution of its Velaro high-speed platform, with 434 to 450 passengers per train depending on configuration. Siemens says the AP 220 is designed for operating speeds up to 220 mph (354 km/h); Brightline West plans service at up to 200 mph (320 km/h). Under the FRA Buy America waiver the first two trainsets are built in Germany and the remaining eight in Horseheads, New York (Siemens announcement, September 2024). According to a July 2026 update to the Nevada High-Speed Rail Authority reported by the Review-Journal, the first two car bodies have been completed and the Horseheads factory is set to open by the end of 2026. Siemens also holds a 30-year maintenance contract.
Power and signalling. Brightline West describes an overhead catenary system along the whole right-of-way, all-new track, and no grade crossings. According to the FRA, Brightline West selected the European Rail Traffic Management System (ERTMS) because it is service-proven at higher speeds in Europe; the FRA notes that ERTMS has not yet been certified for operation in the United States and that the domestic I-ETMS is approved up to 125 mph (200 km/h). No supplier is named.
Civil works. Brightline West counts more than 160 structures (viaducts and bridges), 3.4 million square feet (316,000 m2) of retaining walls and about 322 miles (518 km) of overhead lines. The FRA environmental assessment for the Cajon Pass section describes a 49-mile (79 km) segment, 48 miles (77 km) of it inside the I-15 right-of-way, built under a lease from Caltrans, with one new traction power substation in the Hesperia area, 60-minute headways and a top speed of about 140 mph (225 km/h). Track laying, signalling, catenary and substations start after each civil contractor hands over its segment.
Economic Impact
Jobs. At the April 2024 groundbreaking Brightline West projected more than 35,000 jobs over the construction period, of which 10,000 direct union construction roles under project labour agreements with the building trades, and 1,000 permanent operations and maintenance positions (its FAQ page now says about 800 permanent jobs). Siemens said the Horseheads, New York plant would employ about 300 people (Manufacturing Dive, September 2024).
Wider claims. The company projected an economic impact above $10 billion, and more than $800 million of I-15 corridor improvements as part of the project. These are Brightline West's own projections; ridership forecasts have varied across documents and are not reproduced here. The company has said fares are not yet set and are expected to be 'on par with the cost of gas and parking'.
Environmental Impact
Operational claims. Brightline West states that its trains will reduce emissions by over 400,000 tons of CO2 a year and cut vehicle miles travelled by more than 700 million a year (April 2024 release). These are company figures.
Habitat and mitigation. The 2011 Record of Decision and the 2023 Finding of No Significant Impact for the Cajon Pass segment each carry mitigation commitments and a Biological Opinion, published by the FRA. Brightline West says it will build three wildlife overpasses, primarily for bighorn sheep, with the California Department of Fish and Wildlife and Caltrans.
Challenges & Controversies
Cost. Brightline West put the project at $12 billion at the April 2024 groundbreaking. Bond Buyer and Fox LA report an intermediate figure of $16.1 billion. A US Department of Transportation list reported by the Las Vegas Review-Journal on 2 October 2025 shows $21.05 billion, which a company spokesperson confirmed; other outlets reported $21.5 billion. Michael Reininger, then Brightline's chief executive and now managing director of Brightline West, attributed the increase to higher construction costs, as reported by Bloomberg. The Review-Journal gave $20.1 billion in October 2026, and a company securities filing reported by KTNV says about $20.9 billion remains to be spent.
Financing. In November 2025 Brightline West exchanged its $2.5 billion of Series 2025A private activity bonds for up to $1.8 billion of senior secured Series 2025B bonds, with about $700 million repurchased, and pledged to raise at least $400 million of equity by 31 March 2026 (company release, 20 Nov 2025). The equity was not raised by that deadline and bondholders have extended it several times. On 3 November 2026 the Bond Buyer reported that a majority of bondholders agreed to delay the 2 November mandatory tender and the equity deadline to 12 January 2027, the sixth extension; the bond trustee appointed RPA Advisors as cash manager to supervise spending, and spending for the rest of 2026 was reduced to just under $43 million. The company applied for a $6 billion RRIF loan on 26 September 2025; the loan was still in pre-application review on 3 November 2026 and no invitation to apply had been reported. On 27 October the company called its financing effort not new and part of ongoing discussions. In March 2026 it told investors it was also pursuing a roughly $4 billion bank loan, which depends on the federal loan. Also in March 2026 Reininger told investors that underground works, columns, the first elevated decks and 1,300 feet (400 m) of drainage were complete, without saying where (Bond Buyer). Alon Levy, a fellow at NYU's Marron Institute, wrote to Smart Cities Dive on 22 June 2026 (published 17 September) that private-sector plans are not really workable and predicted Brightline West would pivot to more federal funding; Joseph Schwieterman of DePaul University said federal support is probably needed while welcoming private investment.
Opening date. The Los Angeles 2028 Olympics were the early goal; bond documents reported by KTNV in early 2025 said December 2028; the company said in January 2026 that completion was scheduled for late 2029 and on 27 October 2026 that it expects to open in 2029. The company also says about four years once financing closes, which would run past 2029 if financing closes after 2026 (Spotatrain calculation). The Review-Journal writes that late 2029 is the earliest possible.
Leadership. President Sarah Watterson stepped down in August 2026 and became a special adviser (Bloomberg Government, 17 Aug 2026); Adrian Share is interim president and Reininger leads delivery (Review-Journal).
Buy America waiver. The FRA waiver, effective 29 May 2024, covers the first two complete trainsets, the car shells for all ten trainsets, Eurobalises and Euroloops, counting heads and axle counter sensors, a truck press test stand, turnout systems including derailers, and fire alarm systems, finding no domestic maker of service-proven trainsets above 125 mph. Alstom, which also bid, sued; a federal court in Washington, D.C. dismissed the case in late 2025 without ruling on the waiver's validity, finding Alstom had not shown standing, and Alstom has filed a notice of appeal.
Relationship with Brightline Florida. The company says Brightline West and Brightline Florida are separate, with their own financing and project structures, and that Florida developments would not affect the project (spokesperson, 27 Oct 2026). Brightline Holdings LLC and 16 other parent companies of the Florida business filed for Chapter 11 in New Jersey on 24 September 2026; Brightline West and the Florida operating company are not debtors. Mass Transit reports that one of the debtors holds about 40% of Brightline West; the Bond Buyer (5 Oct 2026) reports that subordinated Florida bondholders hold liens on Brightline West's equity, that a fund, CK Opportunities, has challenged in court since 2023 the 2022 takeover of that equity by a Fortress entity, and quotes a lawyer who considers the structures less independent than before. No response from the company was in that article. No Florida financial figure is used on this page for Brightline West.
Watch this project live
A railway webcam covers this project — see what is running right now.
- Watch live
Barstow, California — PTZ Camera
PTZ camera on the BNSF Needles Subdivision, hosted at Barstow Station
Project Timeline
FRA Record of Decision for DesertXpress
After a draft statement in March 2009 and a final environmental impact statement in March 2011, the Federal Railroad Administration issued its Record of Decision for the Las Vegas to Victorville high-speed passenger train project, later renamed XpressWest and then Brightline West.
SourceBrightline agrees to acquire XpressWest
Brightline, a subsidiary of Fortress Investment Group, announced it would acquire XpressWest, the holder of a federally approved corridor beside Interstate 15, with construction then expected in 2019 and service in 2022.
SourceFRA finding for the Cajon Pass segment
The Federal Railroad Administration signed a Finding of No Significant Impact for the 49-mile Victor Valley to Rancho Cucamonga segment (top speed about 140 mph), after an environmental assessment signed on 26 October 2022.
Source$3 billion federal grant announced by President Biden
President Joe Biden visited Las Vegas on 8 December 2023 to highlight a $3 billion federal award for the Brightline West line, part of more than $6 billion for high-speed rail; NDOT states it was awarded the funds in partnership with Brightline West.
SourceGroundbreaking ceremony in Las Vegas
Brightline West broke ground at the planned Las Vegas station site before more than 600 attendees, with speakers including Transportation Secretary Pete Buttigieg, Brightline founder Wes Edens, Nevada Governor Joe Lombardo and Senators Catherine Cortez Masto and Jacky Rosen.
SourceSiemens named preferred bidder for the trainsets
Brightline West selected Siemens Mobility as preferred bidder for ten seven-car American Pioneer 220 trainsets; the contract was finalised and the Horseheads, New York factory announced on 9 September 2024.
Source$3 billion FRA grant agreement signed
The Federal Railroad Administration signed the $3 billion grant agreement with the Nevada Department of Transportation, the grantee.
Source$6 billion RRIF loan request listed by the Build America Bureau
Brightline West appeared on the Bureau credit assistance pipeline with a $6 billion request on 26 September 2025 and an estimated project cost of $21.05 billion, which a company spokesperson confirmed to the Las Vegas Review-Journal on 2 October 2025.
SourceSeries 2025A bond exchange announced
Brightline West announced a private exchange of $2.5 billion of Series 2025A bonds for up to $1.8 billion of senior secured Series 2025B bonds, about $700 million repurchased, and a pledge to raise at least $400 million of equity by 31 March 2026.
SourceCompletion target moved to late 2029
Brightline West told FOX5 that the line was now scheduled for completion by late 2029, and described the project as in its civil construction phase; no date had been set for laying track.
SourceStill awaiting the federal loan
Brightline West told FOX5 it was still waiting on the $6 billion federal loan, and had told investors it was also pursuing a roughly $4 billion loan from a banking consortium.
SourcePresident Sarah Watterson steps down
Bloomberg Government reported that Sarah Watterson had stepped down as president of Brightline West and become a special adviser; Mike Reininger remained managing director.
SourceReview-Journal: momentum has all but halted
The Las Vegas Review-Journal reported that momentum on the project had all but halted, with the Las Vegas station garage unfinished and crews not seen in months, while the company said it was focused on finalising financing to move into full-scale construction.
SourceBondholders delay mandatory tender to 12 January 2027
The Bond Buyer reported that a majority of bondholders agreed to delay the 2 November mandatory tender, and the $400 million equity deadline, to 12 January 2027 (the sixth extension), and that the bond trustee appointed RPA Advisors as cash manager to supervise spending.
SourceVideos
Brightline West: The $12 BILLION Railway America Has Been Waiting For
Photos
West Palm Beach Brightline Station
External Resources
Official resources
news
Frequently Asked Questions
When will Brightline West open?▾
How fast will the trains go?▾
How much does the project cost and who is paying?▾
Where will the line start and end?▾
How will the line cross the Cajon Pass?▾
What trains will Brightline West use?▾
Is construction under way?▾
Is Brightline West connected to the Brightline Florida restructuring?▾
Help improve this page
Spotted something out of date or incorrect? Let our community know.
Explore around this project
8 places on Spotatrain within 25 km of this project — 3 spots and 5 live cams.











